LAN installation | The cost of SCN construction services
|
The cost of SCS
construction services
When prices for the construction of SCS are setting up, each customer receives a discount on all passive
equipment, not less than 3% from its retail price. The following prices can vary depending on the complexity of
terms and amount of works that have to be done. On large industrial nets, after approval of the project
(including passive equipment) the average price per port is negotiated with the customer.
Name of service
|
Units of measurement
|
Price, UAH
|
Installation and setting up of equipment
|
Patch panel crossing (cutting and preparing the cable, cross-connect on the patch panel)
|
per 1 port
|
7
|
RJ-45 jack wiring with test of connection
|
1 unit
|
5
|
RJ-11/RJ-12 jack wiring with test of connection
|
1 unit
|
3
|
Installing the wall cabinet
|
1 unit
|
150
|
Assembling the wall cabinet
|
1 unit
|
50
|
Installation of equipment in the cabinet (patch panel, organizer, active equipment, UPS)
|
per 1 unit
|
10
|
Installation of outlets
|
Installation of outlet (1 RJ-45 (computer))
|
1 unit
|
25
|
Installation of outlet (2 RJ-45 (computer))
|
1 unit
|
40
|
Installation of outlet (1 RJ-11 (telephone))
|
1 unit
|
20
|
Installation of outlet (2 RJ-11 (telephone))
|
1 unit
|
30
|
Installation of outlet (RJ-45 (computer) + RJ-11 (telephone))
|
1 unit
|
40
|
Installation of cable routes
|
Hole in concrete/brick walls
|
1 hole
|
45
|
Hole in the walls of lightweight materials
|
1 hole
|
15
|
Installation of cable channels (box, metal tray) on brick and concrete structures
|
1 m
|
7
|
Cable installation
|
Cabling installation
|
1 m
|
5
|
Installing cable in boxes/metal trays
|
1 m
|
2
|
The coefficient for installing of cable at an altitude of more than 3 meters
|
1,5
|
The coefficient for installing of cable in hard to reach areas
|
1.5
|
The coefficient for outdoor works in winter
|
1.5
|
The coefficient for outdoor works in summer
|
1.5
|
The coefficient for the works on weekend
|
2
|
|
|